Mr R - Upleadon

Bathroom Installation

The Process:

  1. We removed the old suite
  2. The downlighters wiring was modified
  3. Then the downlighters were put in
  4. The room was re-plastered
  5. A plinth was built for the shower
  6. Wiring for the shower lights was put in
  7. The floor was then plied
  8. The shower tray was fitted and tiled around
  9. Shower panels were fitted
  10. Then the new bathroom suite was fitted
  11. A shower panel was used to go around the bath as a bath panel
  12. Finally the cushion floor was fitted to the floor

RETURN TO PREVIOUS PAGE

Stewart Kitchens  Bathrooms Bathroom 6 Image 10
Stewart Kitchens And Bathrooms Mr R Upleadon 10
Stewart Kitchens And Bathrooms Mr R Upleadon 8
Stewart Kitchens And Bathrooms Mr R Upleadon 1
Stewart Kitchens And Bathrooms Mr R Upleadon 2
Stewart Kitchens And Bathrooms Mr R Upleadon 4
Stewart Kitchens And Bathrooms Mr R Upleadon 5
Stewart Kitchens And Bathrooms Mr R Upleadon 6
Stewart Kitchens And Bathrooms Mr R Upleadon 7

What our customers think
"We're so glad we found Les! Les was reliable, punctual, communicative, friendly without being intrusive and most importantly, very good at his job."
Alex Vernon Kitchen Renovation

 

GET IN TOUCH

Simply fill in the form below and we'll get back to you as soon as possible.

 

Invalid Input
Invalid Input
Invalid Input
Invalid Input
Invalid Input
Invalid Input